Complete site planning for commercial, industrial, and residential projects — from the first survey through final construction clearance.

Civil Engineering Land Surveying
The Challenge

New York Development
Is Complex. It Doesn't
Have to Be Overwhelming.

Development projects in New York State involve more agencies, more timelines, and more moving parts than most people expect. Whether you're subdividing a parcel, building a commercial site, or dealing with a FEMA flood zone issue — the path from concept to construction clearance requires careful coordination.

The good news: it's a navigable process when you have the right team. Every milestone is something McMahon LaRue handles on your behalf, every day.

01

Up to 8 Agencies

A single commercial site plan in Monroe County may require Town Planning Board, NYSDEC, FEMA, County DOT, and NYSDOT submissions — simultaneously.

02

2–16 Weeks Per Agency

Each agency runs its own timeline. Knowing which to sequence first — and which can run in parallel — is the difference between 6 months and 18 months.

03

One Team, Start to Finish

MLA provides both the engineering and the survey — no hand-offs between firms, no coordination gaps, one point of contact for the entire project.

Our Process

The MLA Project Pathway

A six-phase framework built across decades of New York State projects — residential, commercial, and industrial.

Land Surveying
Civil Engineering
Surveying
01

Site Assessment

Deliverable included

What We Do

  • Conduct boundary and topographic survey of the parcel
  • Review current zoning, setbacks, and land use regulations
  • Identify environmental constraints: wetlands, floodplain, steep slopes
  • Analyze utility availability and site access options

You Decide

  • Confirm project goals, program, and overall vision
  • Identify budget parameters and timeline expectations

Deliverable

Base survey + constraints summary

Civil Engineering
02

Preliminary Design

Deliverable included

What We Do

  • Develop one or more concept site plan layouts
  • Evaluate access, parking, stormwater routing, and utilities
  • Prepare preliminary opinion of probable construction cost
  • Identify all agencies that will require submissions or approvals

You Decide

  • Select preferred design concept to advance
  • Confirm project budget and acceptable cost range
  • Authorize proceeding to Phase 03

Deliverable

Preferred concept plan + approval roadmap

Civil Engineering
03

Agency Coordination

Duration: 2–4 Weeks

Deliverable included

What We Do

  • Schedule and lead pre-application meetings with Town Planning Board
  • Coordinate requirements with DEC, FEMA, County, and NYSDOT as applicable
  • Confirm submission checklists, fees, and hearing schedules for each agency
  • Prepare project narrative and initial application materials

You Decide

  • Review agency feedback and confirm project direction
  • Address any scope changes required before final design begins

Deliverable

Agency submission checklist + pre-application meeting summary

Civil Engineering
04

Final Design

Deliverable included

What We Do

  • Produce full site plan drawing set: grading, drainage, utilities, geometry
  • Prepare Stormwater Pollution Prevention Plan (SWPPP) if required
  • Complete subdivision plat or land division documents if applicable
  • Coordinate with architects, structural, and specialty engineers

You Decide

  • Approve final site plan layout before agency submission
  • Confirm phasing strategy if project is to be built in stages

Deliverable

Full drawing set + Stormwater Pollution Prevention Plan

Civil Engineering
05

Agency Approvals

Duration: Varies by agency

Deliverable included

What We Do

  • Submit applications to all required agencies simultaneously where possible
  • Prepare presentations and appear at Planning Board and ZBA hearings
  • Respond to agency comment letters; revise drawings as needed
  • Track all submission deadlines, re-submission windows, and hearing schedules

You Decide

  • Attend key hearings (optional but often valuable)
  • Authorize any project modifications required by agencies

Deliverable

All required agency approvals and permits issued

Surveying
06

Construction Support

Deliverable included

What We Do

  • Provide construction stakeout: lot corners, building corners, road grades, utility lines
  • Monitor site for compliance with approved grading and drainage plans
  • Prepare as-built survey upon construction completion
  • Support building permit sign-off and certificate of occupancy process

You Decide

  • Coordinate stakeout schedule with contractor's site plan
  • Authorize any field condition changes that affect the approved plans

Deliverable

As-built survey + certificate of occupancy support documentation

Throughout the process, you will always know where your project stands. Clear communication at every phase milestone — no black holes, no surprises at the finish line.

The Approval Landscape

Agencies You'll Navigate

Most site developments in Monroe and surrounding counties touch several of these agencies. MLA knows the submission checklists, the hearing schedules, and the people at each. Not every project requires all of these approvals.

Agency 01

Town Planning Board

4–8 wks

Site plan and subdivision approvals; SEQR review; zoning compliance.

Agency 02

Zoning Board of Appeals

4–6 wks

Area and use variances; special permits; interpretation of zoning code.

Agency 03

NYSDEC

30–90 days

Stormwater SPDES permits (SWPPP); wetland permits; DEC regulated activities.

Agency 04

FEMA / NFIP

60–180 days

Flood zone determinations; Letters of Map Amendment (LOMA); elevation certificates.

Agency 05

Monroe County DOT

4–12 wks

Driveway and road access permits on county roads; sight distance; turn lanes.

Agency 06

NYSDOT

6–16 wks

State highway access permits (Routes 31, 441, 104 corridor, etc.).

Agency 07

Town Building Department

2–6 wks

Building permit issuance after all site approvals are granted; CO sign-off.

Agency 08

Army Corps of Engineers

60–120 days

Section 404 permits for impacts to navigable waters or regulated wetlands.

Site Development Work

Projects We've Delivered

Photo Coming
Subdivision

Meadow Ridge Estates

Webster, NY

12-lot residential subdivision on a 14.3-acre parcel — boundary survey through Planning Board final plat.

  • Boundary Survey
  • Subdivision Design
  • NYSDEC SPDES
  • Monroe County DOT
  • Stormwater Management
Photo Coming
Site Development

Penfield Professional Park

Penfield, NY

Site plan approval for a 4,800 SF professional office building on a 1.2-acre parcel.

  • Site Plan Design
  • Grading & Drainage
  • Monroe County DOT
  • Town Planning Board
Photo Coming
FEMA Compliance

Lakeside Cove LOMA

Fairport, NY

Letter of Map Amendment resulting in removal from FEMA Special Flood Hazard Area — eliminating mandatory flood insurance.

  • Elevation Certificate
  • LOMA Application
  • FEMA Coordination